Botanica / Education / Schools

Extension and repair, Gymnasium No. 6

Extension and repair, Gymnasium No. 6 Extension and repair, Gymnasium No. 6 Extension and repair, Gymnasium No. 6 Extension and repair, Gymnasium No. 6

Description

Gymnasium No. 6 in the Botanica sector of the capital is to be completely renovated. The Chisinau City Hall has allocated 150 000 thousand lei for this purpose.

The repair works were initiated in 2021, after the contract for the design and implementation of the works was concluded. During the same year, 20% of the repairs were completed.

In the first two months of 2022, reconstruction works were 32 percent completed.

Subsequently, the renovation process of Gymnasium No. 6 was halted due to the price increase of construction materials.

The Chisinau City Hall plans to complete the repair works in full as soon as possible, with the project being transferred to 2023.

Investment: 150 000 lei