Chișinău City Hall has built a new U-turn lane at the intersection of București Street and Dacia Boulevard.
Complex works were carried out for this project: foundation excavation, sand ballast and crushed stone layers, installation of curbs and manholes, followed by asphalt paving. The total work area is approximately 750 m².
In addition, road signs were installed and markings were painted according to the project, making the lane fully operational and safe for traffic.
This intervention was necessary to ease traffic congestion at one of the busiest intersections in the city and to ensure safer U-turn maneuvers.