In 2020, the rehabilitation of sidewalks in the historic center of the city began.
The first to benefit from the modernization of pedestrian areas were the streets Mitropolit Gavriil Banulescu Bodoni and Alexandr Puskin, in the perimeter of Alexei Mateevici Street and Albisoara Street.
According to the project, the following works were carried out:
- pavements were paved in two
colours - white and black;
- new kerbs were installed;
- green areas were
landscaped;
- street lighting was rehabilitated;
- access for people with reduced
mobility was facilitated;
- urban decorative elements were installed;
- parking
places were installed on certain parts of the street.
The cost of the works was 22.8 million lei, money allocated by the Government and some economic agents
Investment: 22 800 000 lei