Within the framework of the project the alleys were rehabilitated and the green spaces were landscaped.
The works included:
- rehabilitation and paving of pedestrian walkways;
- installation of
curbs to delimit the areas;
- landscaping of green areas;
- installation of
street furniture for the comfort and safety of citizens;
- installation of a
public lighting system to ensure safety at night.
The total budget allocated to the works was 1 216 800 lei.
The project was completed in 2022.
Investment: 1 216 800 lei